The Big Branch Greenway Will Reach Both Sides of I-440 Before It Crosses It

Big Branch is the creek that runs behind North Hills on the east side. It passes the foot of Tributary, the Kane Realty apartment building now rising in the North Hills Innovation District. It runs under I-440 and continues south through Midtown toward the Crabtree Creek Trail. Raleigh has drawn a greenway along that creek in its 1976, 1989 and 2022 greenway master plans. In the 2022 plan it ranked first among 98 proposed trail projects.

Three of its segments are now funded, mapped and in detailed design. On the city's schedule, the south half and a key northern piece will be finished by late 2028. The piece that joins them over the Beltline has no money and no date. The Big Branch Greenway will arrive in North Hills as two halves, and the gap between them will sit on I-440.

A Trail Split Into Six Segments

The full route is more than 3.5 miles. When finished, it will run from the Crabtree Creek Trail to Cedar Hills Park, with planned connections to Kiwanis Park and Eastgate Park along the way. The city is building it in six segments, through a mix of city investment, private development and future planning. Here they are from south to north:

  1. Segment 1A, Crabtree Creek Trail to Six Forks Road. It follows the east side of the creek, runs along part of a parking area and Selby Drive, and brings trail users to the signal at Selby Drive and Six Forks Road. Paid for by the Parks Bond.
  2. Segment 1B, Six Forks Road to Wake Towne Drive. Paid for by the Parks Bond.
  3. Segment 2, the Midtown Multimodal Bridge over I-440. A Raleigh Transportation project.
  4. Segment 3, from the bridge to St. Albans Drive. To be built by a private developer.
  5. Segment 4, St. Albans Drive to Hardimont Road. It runs along the east side of Big Branch and ties into the Quail Hollow Drive Green Street project. Paid for by the Parks Bond.
  6. Segments 5 and 6, north of Hardimont Road toward Sandy Forks Road. Segment 5 is a Raleigh Transportation project. Segment 6 is still at the feasibility-study stage.

Who builds each piece decides how fast it arrives. The bond-funded segments have a construction schedule. The private segment moves with Kane Realty's development calendar. The transportation segments, including the bridge, depend on funding that hasn't been found yet.

The Bond Pieces Have a Date

Segments 1A, 1B and 4 are the core of what the city calls the Big Branch Greenway Connector. City Council approved their alignments on November 18, 2025. Kimley-Horn is the design consultant. According to the city's project page, property acquisition runs from summer 2026 through fall 2027 and construction from late 2027 to late 2028.

The money comes from two sources. The city's November 2025 schematic design presentation lists a $5.68 million budget: $4.48 million from the 2022 Parks Bond, which passed with 73% of the vote, and $1.2 million from Raleigh Stormwater. It also calls this the only new trail construction project in that bond. The stormwater share pays for stabilizing the streambank along Big Branch. That makes the project a creek restoration as well as a path.

Segment 1B shows what kind of trail this will be. The city weighed seven routes between Six Forks Road and Wake Towne Drive, from street-side options along Plantation Road to two creekside alignments. Staff recommended the Streamside West route. In a spring 2025 survey with 1,628 participants, 62% chose it. The presentation describes it as a 10-foot path with gentle grades, suited to "pedestrians, bikes, strollers, wheelchairs," with minimal tree removal and "a more natural experience."

Getting the land comes before building. An August 18, 2026 City Council agenda item lists 20 private properties affected by the connector. The item recommended authorizing condemnation only for property interests not voluntarily conveyed by February 16, 2027. Negotiations can continue until that date. That February date is the next one on the project's calendar.

North of the Beltline, Kane Sets the Pace

Above I-440, the trail runs through the North Hills Innovation District, and private development drives the timing. In its October 1 development roundup, Raleigh Magazine reported that Kane Realty is extending a greenway that will eventually tie into the city's trail network. It described the "initial segment from St. Albans Drive to Hardimont Road" as "now open." The city's public Segment 4 covers the same two streets. On the city's schedule it is still in design, with construction set for late 2027 to late 2028.

The same article describes Kane's next phase. A "boardwalk-esque pedestrian bridge" will connect St. Albans Lofts to Tributary and eventually extend toward the planned bridge over I-440. WRAL reported that Tributary broke ground in January 2026 and is expected to finish by spring 2028. That is the building's schedule. No date has been published for the boardwalk itself. Raleigh Magazine also notes that Kane bought an additional 28 acres this year to push the district's footprint to Wake Forest Road. As that land develops, more of the creek corridor comes into play.

Segment 4 also joins a separate city project. The Quail Hollow Drive Green Street project lists construction as in progress. Its first phase covers active-mobility improvements, and later phases cover stormwater work, resurfacing, traffic calming and sidewalks.

Where the Two Halves Would Meet

Segment 1B ends at Wake Towne Drive. The News & Observer reported in 2023 that the proposed Midtown Multimodal Bridge would cross I-440 between Six Forks and Wake Forest roads. It would link St. Albans and Navaho drives on the north side with Barrett and Wake Towne drives on the south. The bond-funded south half ends on the street where the bridge would come down. The northern pieces begin at St. Albans Drive, where the other end of the bridge would land.

The bridge has been in planning since the city adopted the Walkable Midtown plan in December 2020, which named it one of the plan's "Seven Big Moves." The city's Fall 2026 update shows how far it has come:

The Midtown Multimodal Bridge project has completed its 30% design phase. ... Funding for construction and the project timeline have not yet been determined.

The same update says the project team is working with property owners and development teams on both sides of the bridge before the next phase of design. Segment 3, the private stretch from the bridge to St. Albans Drive, depends on it. That segment has no reason to connect to anything until the bridge exists.

The bond-funded segments were set up to stand on their own. Segment 1A connects the Crabtree Creek Trail to Six Forks Road at Selby Drive, so a walker from Midtown's south side can reach the city's main trail network without crossing the Beltline at all. Segment 4 gives the Innovation District a creekside link between St. Albans Drive and Hardimont Road, connecting to Quail Hollow Drive. Each half works for the people who live near it. A full Crabtree-to-Cedar Hills route, with North Hills in the middle, still depends on the bridge.

The Dates Between Now and 2028

For anyone tracking the trail from a North Hills address, these are the dates the city and the builders have published:

  • February 16, 2027. Deadline for voluntary land negotiations on the bond-funded segments under the August 2026 Council item.
  • Fall 2027. End of property acquisition, and the city's target for completing design, permitting and bidding.
  • Late 2027. Construction starts on Segments 1A, 1B and 4.
  • Spring 2028. Expected completion of Tributary, the building Kane's boardwalk phase is meant to reach.
  • Late 2028. Target completion for the bond-funded trail.

The Midtown Multimodal Bridge has no date on that list because the city hasn't set one. The trail Raleigh first drew in 1976 will meet Wake Towne Drive on the south side of I-440 and St. Albans Drive on the north side, and those two streets will stay unconnected until the bridge is funded.

The city has chosen the trail's route, and with it which streets and homes will sit near a creekside greenway. If you own a home near Big Branch and want to see how a future trail fits into the way your property is presented, Eric Mikus can walk the route with you and build that into your marketing. Request a Luxury Home Valuation to start the conversation.

Please complete the following form to download our home seller’s guide

Sending...
Successfully sent!
eBook Image
Bright white kitchen with a marble island, dark wood base, bar stools, and exposed ceiling beams.

How Much is Your Home Worth?

  • Instant property valuation
  • Expert advice
  • Sell for more

Work With Eric

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.

Let's Connect

Follow Me on Instagram